Contractor’s Material and Test Certificate for Underground Piping

Procedure

Upon completion of work, inspection and tests shall be made by the contractor’s representative, and witnessed by an owner’s representative. All defects shall be corrected and system left in service before contractor’s personnel leave the job.

This certificate shall be filled out and signed as indicated. Copies shall be prepared for approving authorities, owners, and contractor. It is understood the owner’s representative's signature in no way prejudices any claim against contractor for faulty material, poor workmanship, or failure to comply with the approving authority’s requirements or local ordinances.

Plans 


Accepted by approving authorities (names): DRAPER CITY FIRE DEPARTMENT

Address: 1020 East Pioneer Road Draper, Utah 84020

Installation conforms to accepted plans
 
Equipment used is approved
 

Instructions


Has person in charge of fire equipment been instructed as to location of control valves and care and maintenance of this new equipment?
 
Have copies of appropriate instructions and care and maintenance charts been left on premises?
 

Location 



Underground Pipes and Joints


Pipe conforms to __________ standard
 
Fitting conforms to __________ standard
 
Joints needed anchorage clamped, strapped, or blocked in accordance with NFPA standards.
 

Test Description

Flushing: Flow the required rate until water is clear as indicated by no collection of foreign material in burlap bags at outlets such as hydrants and blow-offs. Flush at flows not less than 390 gpm for 4-in. pipe, 880 gpm for 6-in. pipe, 1560 gpm for 8-in. pipe, 2440 gpm for 10-in pipe, and 3520 gpm for 12-in. pipe. When supply cannot produce stipulated flow rates, obtain maximum available.

Hydrostatic: Hydrostatic tests shall be made at not less than 200 psi for 2 hours or 50 psi above static pressure in excess of 150 psi for 2 hours.

Hydrostatic Testing Allowance: Where additional water is added to the system to maintain the test pressures, the amount of water shall be measured and shall not exceed the limits of the following equation.

Image of test description formula

L= testing allowance (makeup water), in gallons per hour
S= length of pipe tested, in feet
D = nominal diameter of pipe, in inches
P = average test pressure during the hydrostatic test, in psi gauge.

 

 


Underground Pipes and Joints


New underground piping flushed according to__________ standard by (company)
 
How flushing flow was obtained
 
Through what type opening
 
Lead-ins flushed according to standard by __________ (company)
 
How flushing flow was obtained
 
Through what type opening
 

Hydrostatic Test


Joints Covered
 

Leakage Tests


Hydrants


All operate satisfactorily
 

Control Valves


Water control valves left wide open
 
Hose threads of fire department connection and hydrants interchangeable with those of fire department answering alarm.
 

Remarks


Signatures



Tests witnessed by




Sign up for Notify Draper

Receive notifications via email or text from Draper City regarding emergencies, traffic/construction alerts, news and events.

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.